Construction Update - September 2011
September 30
- Hospital Construction foundation and underground utility work continues.
- Utility Work on Mark West Springs Road continues.
- On Site Permit construction at South parking is complete and landscaping is being planted in bio-swales. North parking area is underway.
September 12
- Hospital Construction foundation and underground utility work continues.
- Surcharge process is complete and the final results have been accepted by the State of California.
- Utility Work on Mark West Springs Road is underway with PG&E.
- On Site Permit construction at South parking is paved and will be completed this month. The fire main installation has begun as well as joint trenching for electrical and natural gas service.
Underground plumbing installation continues with the hospital foundations.
PG&E is working on the power poles.
Reinforcement and concrete are being placed up to 9 ft below the surface.