Construction Update - May 2011
May 25
- Surcharge Phase 2 soil relocation from the Phase 1 location is complete. Monitoring locations have now been set at the top of the pile to record settlement progress.
- 3D Modeling of the hospital building continues with the addition of medical equipment and furnishings to the interior model.
- Artwork was repositioned on the site, under the supervision of the artist, to a safe location away from construction.
May 11
- Waste Water Pond Decommissioning is complete.
- Surcharge Phase 2 has begun with the stabilization of the bottom of the ponds and the placement of the settlement monitoring devices at the bottom of the excavation.
- 3D Modeling of the hospital building continues with weekly coordination meetings.
Soil settlement monitors are set up