Construction Update - March 2011
March 30
|
March 9
Back to top
Back to top
March 30
- Surcharge settlement of Phase 1 is
complete and approved by OSHPD. Phase 2 will begin after the pond is
decommissioned. - Waste Water Pond Decommissioning is mostly complete. Final work will take place after rain stops and the ponds can be drained.
- 3D Modeling of the hospital building is underway at the project site.
Back to top
March 9
- Surcharge settlement of Phase 1 is complete and approved by OSHPD. Phase 2 will begin after the pond is decommissioned.
- Waste Water Pond Decommissioning has completed biosolids removal. Rock, trees, and debris will be removed next to complete this activity.
- Office trailers are complete and the team is co‐located on site.
Back to top
Construction Team Working On Site
Office Trailer
Waste Water Pond Decommissioning
Piping in the Ground