    Construction Update - June 2011

    June 22

    • Surcharge Phase 2 monitoring continues and settlement continues on track.
    • On Site Permit construction begins in the South parking area and the storm water detention basins.
    • Artwork foundations are complete and the relocation is scheduled for this week.
    • Hospital Construction is ready to begin once the permit is issued in July.

    June 8

    • Surcharge Phase 2 monitoring continues and is behaving as forecasted in the geotechnical study.
    • On Site Permit has been issued and has released preparations for this summer’s scheduled work.
    • Artwork foundations are being prepared for the large artwork relocation planned for the end of June.
    Artwork is being relocated
    Artwork is being relocated

    Parking lot is being tilled and graded