Construction Update - June 2011
June 22
- Surcharge Phase 2 monitoring continues and settlement continues on track.
- On Site Permit construction begins in the South parking area and the storm water detention basins.
- Artwork foundations are complete and the relocation is scheduled for this week.
- Hospital Construction is ready to begin once the permit is issued in July.
June 8
- Surcharge Phase 2 monitoring continues and is behaving as forecasted in the geotechnical study.
- On Site Permit has been issued and has released preparations for this summer’s scheduled work.
- Artwork foundations are being prepared for the large artwork relocation planned for the end of June.
Artwork is being relocated
Parking lot is being tilled and graded