Skip Navigation

Display Mode:

  • Choose Default Style
  • Choose High Contrast
Sutter Medical Center Santa Rosa New Hospital
  • Construction Updates
  • Contact Us
  • New Hospital Home
  • About the Project
  • News
  • Images & Videos
  • Frequently Asked Questions
  • Donate
Section TitleNews
    Main content

    Construction Update - January 2012

    January 18

    • Hospital construction of the slab on grade is complete and structural steel will begin within two weeks.
    • Utility work is waiting on AT&T to remove their phone lines so the poles on Mark West Springs can be removed.
    • On site permit road work at the main entry drive continues and will be completed this spring.
    The new sidewalk from the entrance at Mark West Springs Rd to the Well Fargo Center has been completed, improving the access for foot traffic to the Performing Arts Center.
    • About Our Sutter Health Network
    • Contact Us
    • Privacy Policy
    • Accessibility

    © 2011 Sutter Medical Center of Santa Rosa. All rights reserved.