    Construction Update – August 2011

    August 17

    • Hospital construction foundation work continues.
    • Surcharge phase 2 results have been reviewed and accepted. The pile is being spread across the site.

    • Utility work on Mark West Springs Road is ready for PG&E.
    • On site permit construction at South parking lot readies for paving. Grading continues on the rest of the site.

    New concrete has set and the formwork is removed as the team moves to the next area.


    The first large concrete placement of the foundations was successfully completed last week.


    Excavation, reinforcement, and formwork for the hospital foundations are underway.