    Timeline


    9/15 – Construction began
    10/23 – Placement of Phase 1 of soil surcharge process for hospital foundation preparation
    11/1 – Completed all land clearing and site preparation work, sound and security fencing; foundation process of surcharge completed
    12/15 – Completed site pad for construction trailers; Wells Fargo Center connected to sanitary sewer
    12/22 – Completed new sewer line and connection of Wells Fargo Center to public sewer system


    4/1 – Wells Fargo waste water ponds decommissioned and removed
    4/1 – On and off site utility and infrastructure work, complete site grading and preparation begins
    5/1 – Placement of Phase 2 of soil surcharge process for hospital foundation – preparation
    6/1 – On site road and main drive expansion and southwest parking lot construction begins
    7/1 – Excavation of hospital West Wing foundation and rebar installation begins
    8/12 – First hospital West Wing foundation concrete pour
    11/29 – First Concrete Pour in Increment 1, Area D


    1/13 – Last Concrete Pour in Increment 1, Area B
    1/24 – Start of Inc. 1 Steel Erection in Area C
    2/3 – Start of Inc. 4 Foundation Layout and Excavation
    2/10 – Start of Metal Decks in Area C – Shake out, Nelson Studs and Welding
    2/27 – Finish Inc. 1 Steel Erection in Area B
    3/1 – Inc. 4 First Grade Beam Pour
    3/20 – Start of Canopy Erection at ED
    3/26 – Finish Canopy Erection at Main Entrance
    4/05 – Inc. 1 First Concrete Deck Pour in Area C, 2nd Level
    April – Expansion of Mark West Springs Road and new main entry signal
    June – Close in exterior of building
    October – Old Redwood Highway/Mark West Road intersection improvements


    December – Complete interior construction


    October – Hospital occupancy