Timeline

9/15 – Construction began
10/23 – Placement of Phase 1 of soil surcharge process for hospital foundation preparation
11/1 – Completed all land clearing and site preparation work, sound and security fencing; foundation process of surcharge completed
12/15 – Completed site pad for construction trailers; Wells Fargo Center connected to sanitary sewer
12/22 – Completed new sewer line and connection of Wells Fargo Center to public sewer system

4/1 – Wells Fargo waste water ponds decommissioned and removed
4/1 – On and off site utility and infrastructure work, complete site grading and preparation begins
5/1 – Placement of Phase 2 of soil surcharge process for hospital foundation – preparation
6/1 – On site road and main drive expansion and southwest parking lot construction begins
7/1 – Excavation of hospital West Wing foundation and rebar installation begins
8/12 – First hospital West Wing foundation concrete pour
11/29 – First Concrete Pour in Increment 1, Area D

1/13 – Last Concrete Pour in Increment 1, Area B
1/24 – Start of Inc. 1 Steel Erection in Area C
2/3 – Start of Inc. 4 Foundation Layout and Excavation
2/10 – Start of Metal Decks in Area C – Shake out, Nelson Studs and Welding
2/27 – Finish Inc. 1 Steel Erection in Area B
3/1 – Inc. 4 First Grade Beam Pour
3/20 – Start of Canopy Erection at ED
3/26 – Finish Canopy Erection at Main Entrance
4/05 – Inc. 1 First Concrete Deck Pour in Area C, 2nd Level
April – Expansion of Mark West Springs Road and new main entry signal
June – Close in exterior of building
October – Old Redwood Highway/Mark West Road intersection improvements

December – Complete interior construction

October – Hospital occupancy